The Donna Nook managed realignment scheme outline construction programme is as follows:

Table 1: Outline Construction Programme for Donna Nook
 Construction Activity Programme
Pre-construction Site Works;
Vegetation clearance, ecological mitigation, UXO surveys etc.
February - April 2012
Site Establishment April - May 2012
Construction; May - June 2012
Embankments May - October 2012
Habitat creation;
Small ditches, ponds, wetland scrapes, tern islands
May - October 2012
New car park June - September 2012
Remove existing car park August 2012
Landscaping August - October 2012
Porter’s Sluice pumping station May - October 2012
Breach April - June 2013
Site Demobilisation May - June 2013